B-DOCK REPLACEMENT PROJECT
  There have been several requests to make a B-Dock Replacement Project schedule available on line.   Here is a schedule as best I can foresee at the present time.  Please keep in mind that these are ESTIMATES ONLY and that I will be posting updates in this space from time to time.  After actual work begins, you should be able to view progress on the web cam view of the marina on the Nautical Landings Marina home page.  Thanks for your interest in Nautical Landings Marina.
DATE POSTED STARTED or PROJECTED ACTUAL
Wednesday, January 17, 2008 ORIGINATED COMPLETION COMPLETION
  DATE DATE DATE
       
USCE PERMIT FOR PROJECT December 23, 2006 N/A April 1, 2007
       
ASSEMBLE BID PACKAGE April 1, 2007 May 24, 2007 May 24, 2007
       
POST BID PACKAGE / ACCEPT BIDS May 24, 2007 June 14, 2007 * July 10, 2007
       
AWARD BASE CONTRACT July 12, 2007 July 12, 2007 July 12, 2007
       
BUILD NEW DOCKS / SHIP TO Pt Lavaca November 1, 2007 December 15, 2007  December 10, 2007
       
DEMOLISH OLD DOCKS September 4, 2007 September 7, 2007  September 7, 2007
       
ASSEMBLE NEW DOCKS December 10, 2007 March 1, 2008  
       
* No Bids received - - Bid Package re-advertised for opening on Tuesday, July 10, 2007