| B-DOCK
REPLACEMENT PROJECT |
| There
have been several requests to make a B-Dock Replacement Project schedule
available on line. Here is a schedule
as best I can foresee at the present time.
Please keep in mind that these are ESTIMATES ONLY and that I will be
posting updates in this space from time to time. After actual work begins, you should be
able to view progress on the web cam view of the marina on the Nautical
Landings Marina home page. Thanks for
your interest in Nautical Landings Marina. |
| DATE
POSTED |
STARTED or |
PROJECTED |
ACTUAL |
| Wednesday, January 17, 2008 |
ORIGINATED |
COMPLETION |
COMPLETION |
| |
DATE |
DATE |
DATE |
| |
|
|
|
| USCE
PERMIT FOR PROJECT |
December
23, 2006 |
N/A |
April
1, 2007 |
| |
|
|
|
| ASSEMBLE
BID PACKAGE |
April
1, 2007 |
May
24, 2007 |
May
24, 2007 |
| |
|
|
|
| POST BID
PACKAGE / ACCEPT BIDS |
May
24, 2007 |
June
14, 2007 * |
July
10, 2007 |
| |
|
|
|
| AWARD BASE
CONTRACT |
July
12, 2007 |
July
12, 2007 |
July
12, 2007 |
| |
|
|
|
| BUILD
NEW DOCKS / SHIP TO Pt Lavaca |
November
1, 2007 |
December 15, 2007 |
December 10, 2007 |
| |
|
|
|
| DEMOLISH
OLD DOCKS |
September 4, 2007 |
September 7, 2007 |
September 7, 2007 |
| |
|
|
|
| ASSEMBLE
NEW DOCKS |
December 10, 2007 |
March 1, 2008 |
|
| |
|
|
|
|
|
|
|
|
|
|
|
* No Bids received - - Bid Package re-advertised for opening on Tuesday, July 10, 2007